OSHA 10 / OSHA 30 crews250 mi mobilization from Dayton, OH

Founder: Arun Panicker+1 (937) 304-6574arunpanicker@arctechohio.com

Mechanical Piping Contractor / Dayton, Ohio

Liquid cooling piping for the data hall.

IRHX, SFN, and CFN loops. Chilled water mains. Condenser water headers. Every system passes Nitro, Hydro, Glycol, and Flushing before handover.

Headquarters
Dayton, OH
Mobilization
250 mi radius
Core scope
DLC + Hydronic
Crew standard
OSHA 10 / 30

01Data Center Cooling & Hydronic Piping

Data Center
Piping.

Three disciplines. One crew. Rack-level coolant loops through the chilled water plant that feeds them.

01 / 03

Direct-to-Chip (DLC) Cooling

Liquid Piping

Stainless and high-purity coolant loops from the CDU to the rack. We install, pressure test, and fill.

  • IRHXPrimary In-Row Heat Exchangers
  • SFNSecondary Flow Networks
  • CFNCoolant Flow Networks
  • ROMPCatcher ROMP assemblies
  • LC25LC25 coolant filling operations
  • CDUCoolant distribution units and rack manifolds
02 / 03

Chilled & Condenser Water

Hydro Piping

Large-bore chilled water mains, condenser water headers, and closed-loop hydronic distribution.

  • CHWChilled water mains
  • CWCondenser water headers
  • CLClosed-loop hydronic
03 / 03

Mechanical Room Installation

Cooling

Chiller and CRAH/CRAC tie-ins, pump sets, and heat exchanger piping packages.

  • CHChiller tie-ins
  • CRAHCRAH / CRAC tie-ins
  • PMPPump sets
  • HXHeat exchanger packages

Estimator Summary

Scope at a glance.

The six lines a general contractor needs before inviting us to bid.

01Trade scope
Mechanical piping: DLC liquid cooling, hydronic, mechanical room
02Liquid cooling
IRHX, SFN, CFN, Catcher ROMP, LC25 fill
03Test sequence
Nitro > Hydro > Glycol > Flushing
04Safety standard
OSHA 10 field crews / OSHA 30 supervision
05Mobilization
250 mi radius from Dayton, OH
06Point of contact
Arun Panicker, Founder

02Testing & Commissioning Protocol

Four stages.
One sequence.

Every system runs the same order before it carries production coolant. No stage is skipped. No stage is reordered.

  1. 01Nitro Testing
  2. 02Hydro Testing
  3. 03Glycol Testing
  4. 04Flushing
01

Stage 01 / 04N2

Nitro Testing

Dry nitrogen pressure and air leak verification.

The loop is charged with dry nitrogen and held. Joints are proven tight before water or coolant enters the system.

02

Stage 02 / 04H2O

Hydro Testing

Hydrostatic strength and pressure testing at peak operating load.

Piping is filled, brought to test pressure, and held for the specified duration. Every joint is inspected. Results are documented.

03

Stage 03 / 04PG/EG

Glycol Testing

Fluid chemistry, freeze protection, and inhibitor analysis.

Concentration, freeze point, and inhibitor levels are sampled and verified against the specification.

04

Stage 04 / 04FLUSH

Flushing

High-velocity flushing, micronic filtration, and cleanliness verification.

Loops are flushed at velocity through micronic filtration until cleanliness is verified. Cold plates and heat exchangers are protected at handover.

Safety Standard

Trained crews.
Every jobsite.

OSHA 10 is required for every field worker. OSHA 30 is required for every supervisor.

OSHA1010-HOUR

Field

Front-Line Field Crews

Required for every pipefitter, welder, and field crew member on site.

OSHA3030-HOUR

Supervision

Supervisors & Leadership

Required for every site supervisor, foreman, and project lead.

✓ No exceptions on any Arc Tech jobsite.

03About Us

Dayton built.
Ohio wide.

Arc Tech LLC operates from 9667 Quailwood Trl, Dayton, OH 45458. Founder Arun Panicker runs the company.

Our trade scope is data center liquid cooling, hydronic piping, and mechanical room installation. Every loop we install goes through Nitro, Hydro, Glycol, and Flushing before turnover.

Crews mobilize up to 250 mi from Dayton, OH, covering the Columbus / New Albany data center corridor, Cincinnati, and Cleveland.

  • Dayton
  • Columbus / New Albany
  • Cincinnati
  • Cleveland
Founder
Arun Panicker
Headquarters
Dayton, OH 45458
Mobilization
250 mi radius
Test protocol
4 stages

04Contact Us & Bid Portal

Bring us the drawings.

Send drawings, specifications, and schedule. Include pipe sizes, materials, and test requirements.

Bid request Form BR-01

Or email arunpanicker@arctechohio.com